MAY 25, 2004

Agenda Item No. 7



Introduced by the County Services and Finance Committees of the:



INGHAM COUNTY BOARD OF COMMISSIONERS



RESOLUTION AMENDING THE 2001 INGHAM COUNTY PARKS FACILITY

MASTER PLAN



RESOLUTION #04-157



WHEREAS, in 2001, the Ingham County Board of Commissioners adopted a revised Ingham County Parks Facility Master Plan; and



WHEREAS, the Parks Facility Master Plan is intended to provide general guidelines for the orderly development of the County Park system; and



WHEREAS, in order to remain eligible for state and federal grant programs it is necessary that the Parks Facility Master Plan be updated every five years and amended during the life of the plan as necessary; and



WHEREAS, the Ingham County Parks Board recommends to the Ingham County Board of Commissioners that the 2001 Ingham County Parks Facility Master Plan be amended as presented.

THEREFORE BE IT RESOLVED, that the Ingham County Board of Commissioners adopts the 2001 Ingham County Parks Facility Master Plan as amended as presented by the Ingham County Parks Board.

BE IT FURTHER RESOLVED, that the goals and objectives for 2002 through 2006, as stated in the Master Plan, shall be construed as desirable goals only with no implied commitment on the part of the Board of Commissioners to fund any particular recommendation contained therein.



COUNTY SERVICES: Yeas: Thomas, De Leon, Hertel, Severino, Nevin

Nays: None Absent: Swope Approved 5/18/04



FINANCE: Yeas: Grebner, Dedden, De Leon, Thomas, Minter

Nays: None Absent: Lynch Approved 5/19/04



































Ingham County Parks Master Plan SUMMARY

Capital Improvement Schedule (Revised 5/04)

(Changes are in italics & shaded)





Item

Estimated Cost

Funding Sources

2002 2003 2004 2005 2006 Total General Fund State/Fed Grants Private Donations Other
Lansing-Mason-Leslie Corridor

(River Trail - South)

215,000 215,000 56,000 159,000
Play Area/Spray Park - Hawk Island Park 300,000 300,000 100,000 150,000 50,000

(City of Lansing)

MSU-Lake Lansing Connector Trail 90,000 150,000 150,000 390,000 247,500 120,000 22,500
Pedestrian/Bike Trails/Planning

Right of Way Acquisition/Construction

Red Cedar Corridor 90,000 150,000 240,000 195,000 45,000
Lake Lansing North Trail (planning only) 15,000 15,000 15,000
Restroom ~ Burchfield

Overlook ~ Pine Knoll Area

150,000 150,000 150,000
Playground Safety Modifications ~ All Parks 120,000 120,000 120,000 360,000 360,000
Tree Planting ~ Hawk Island 20,000 20,000 20,000
"Sailaway" ~ Lake Lansing South

Barrier-Free Fishing Dock/Native Plant Demonstration Area

118,000 118,000 29,500 88,500
A.D.A. Modifications ~ All Parks 25,000 25,000 25,000 25,000 25,000 125,000 125,000
TOTAL 373,000 295,000 445,000 630,000 190,000 1,933,000 1,298,000 562,500 0 72,500





Revised 05//05/04





Ingham County Parks Master Plan 2005

Capital Improvement Schedule (Revised 05/04)

(Changes are in Italics & Shaded)



Item

Estimated Cost

Funding Sources

2002 2003 2004 2005 2006 General Fund State/Fed Grants Private Donations Other
Lansing-Mason-Leslie Corridor

(River Trail - South)

215,000 56,000 159,000
Play Area/Spray Park - Hawk Island Park 300,000 100,000 150,000 50,000

(City of Lansing)

Red Cedar Trail Study

90,000 45,000 45,000
ADA Modifications 25,000 25,000

TOTAL 2005 630,000 226,000 354,000 50,000




Page 66 of the 2001 Ingham County Parks Facility Master Plan





D. Pave the parking lot.



E. Implement outdoor lighting.

F. Expand the irrigation system



G. Install a vegetative buffer along Marsh Road.



H. Replace deteriorating fencing



V. Rayner Park

A. Construct a drained, irrigated soccer field in cooperation with the Mason School District.

VI. Baldwin Park



A. No improvements or changes are recommended at this time.



VII. Hawk Island Park